University of Victoria (UVic) Exchange
Federal contribution
$1.8M
$1,783,118
Federal share50%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 30, 2021
2022
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- British Columbia Transit
- Construction start
- May 24, 2022(actual)
- Construction end
- Nov 12, 2022(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 1, 2022
- Construction end11 months earlyforecast Sep 30, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58776 in the federal list. How to read these figures.