Back to projects

University of Victoria (UVic) Exchange

Oak Bay, British Columbia

completePublic TransitPTIS
Federal contribution
$1.8M
$1,783,118
Federal share50%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 30, 2021
2022
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
British Columbia Transit
Construction start
May 24, 2022(actual)
Construction end
Nov 12, 2022(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2022
  • Construction end11 months earlyforecast Sep 30, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58776 in the federal list. How to read these figures.