Revitalization of Urban Camlachie
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Plympton-Wyoming
- Construction start
- Sep 23, 2021(actual)
- Construction end
- Dec 1, 2021(actual)