Building Envelope Repairs Bundle 4

Drayton Valley, Alberta

completeHealthcare InfrastructureCVRIS
Federal contribution
$5.9M
$5,882,500
Federal share80%

of $7.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
202220232024
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Alberta Health Services
Construction start
Sep 1, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction end12 months earlyforecast Dec 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58827 in the federal list. How to read these figures.