Nurse Call Systems Upgrades Bundle 1 - Various locations
Federal contribution
$3.9M
$3,934,507
Federal share80%
of $4.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
202220232024
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Alberta Health Services
- Construction start
- Mar 25, 2021(actual)
- Construction end
- Feb 8, 2024(actual)
Against the original forecast
- Construction end11 months earlyforecast Dec 31, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58831 in the federal list. How to read these figures.