Repair of drainage pipes and replacement of the mountain water catchment system
Federal contribution
$2.8M
$2,800,000
Federal share80%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux des Laurentides
- Construction start
- Mar 1, 2021(actual)
- Construction end
- May 3, 2022(actual)
Against the original forecast
- Construction end4 months lateforecast Dec 30, 2021
Also in Rivière-Rouge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58891 in the federal list. How to read these figures.