Replacement of steam supply and condensate return piping throughout the building
Federal contribution
$1.3M
$1,280,000
Federal share80%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Côte-Nord
- Construction start
- Nov 15, 2021(actual)
- Construction end
- Apr 28, 2022(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2021
- Construction end4 months lateforecast Dec 31, 2021