Back to projects

Upgrades to the washrooms

Saint-Louis-du-Ha! Ha!, Quebec

completeVentilationCVRIS
Federal contribution
$240,000
Federal share80%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 13, 2023(actual)
Construction end
Dec 8, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast Oct 14, 2022

Also in Saint-Louis-du-Ha! Ha!

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58907 in the federal list. How to read these figures.