Replacement of the exterior siding of the Carleton Campus

Carleton-sur-Mer, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$580,000
Federal share47%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 31, 2021(actual)
Construction end
Apr 5, 2022(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Mar 1, 2022