Back to projects

Addition of Emergency Back Up Generators

Tyendinaga, Ontario

completeVentilationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 24, 2021(actual)
Construction end
Feb 24, 2022(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Oct 4, 2021
  • Construction end6 weeks lateforecast Jan 14, 2022

Also in Tyendinaga

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58960 in the federal list. How to read these figures.