Addition of Emergency Back Up Generators
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- The Corporation of the Township of Tyendinaga
- Construction start
- Oct 24, 2021(actual)
- Construction end
- Feb 24, 2022(actual)
Against the original forecast
- Construction start3 weeks lateforecast Oct 4, 2021
- Construction end6 weeks lateforecast Jan 14, 2022
Also in Tyendinaga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58960 in the federal list. How to read these figures.