Serpent River Water Treatment Plant Rehabilitation
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of The North Shore
- Construction start
- Aug 19, 2021(actual)
- Construction end
- Oct 15, 2024(actual)
Against the original forecast
- Construction end3 months earlyforecast Dec 31, 2024
Also in The North Shore
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58963 in the federal list. How to read these figures.