John M Parrot Center HVAC Replacement

Lennox and Addington, Ontario

completeVentilationCVRIS
Federal contribution
$189,049
Federal share80%

of $236.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Dec 8, 2021(actual)
Construction end
Jun 24, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Sep 9, 2021
  • Construction end5 weeks lateforecast May 18, 2022