John M Parrot Center HVAC Replacement
Federal contribution
$189,049
Federal share80%
of $236.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- County of Lennox and Addington
- Construction start
- Dec 8, 2021(actual)
- Construction end
- Jun 24, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Sep 9, 2021
- Construction end5 weeks lateforecast May 18, 2022
Also in Lennox and Addington
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58964 in the federal list. How to read these figures.