Grouped laboratories: fitting out for the establishment of Optilab - Associated center
Federal contribution
$856,638
Federal share67%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de la Mauricie-et-du-Centre-du-Québec.
- Construction start
- Oct 11, 2021(actual)
- Construction end
- May 13, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast Sep 1, 2021
- Construction end3 weeks lateforecast Apr 22, 2022
Also in Nicolet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59066 in the federal list. How to read these figures.