Replacement of the generator and electrical distribution components
Saint-Pierre-les-Becquets, Quebec
Federal contribution
$352,586
Federal share80%
of $440.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de la Mauricie-et-du-Centre-du-Québec.
- Construction start
- Sep 8, 2021(actual)
- Construction end
- Aug 23, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 21, 2021
- Construction end9 months lateforecast Dec 1, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59073 in the federal list. How to read these figures.