Back to projects

Replacement of the generator and electrical distribution components

Saint-Pierre-les-Becquets, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$352,586
Federal share80%

of $440.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 8, 2021(actual)
Construction end
Aug 23, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 21, 2021
  • Construction end9 months lateforecast Dec 1, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59073 in the federal list. How to read these figures.