Boiler room upgrades and conversion of boilers to natural gas

Montmagny, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$121,957
Federal share80%

of $152.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 17, 2021(actual)
Construction end
Dec 22, 2023(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jun 1, 2021

Also in Montmagny

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59254 in the federal list. How to read these figures.