Miramichi District Garage - Overhead Door Replacement

Miramichi, New Brunswick

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$142,603
Federal share80%

of $178.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of New Brunswick
Construction start
Apr 16, 2021(actual)
Construction end
Oct 16, 2021(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 16, 2021
  • Construction end2 months earlyforecast Dec 31, 2021