Flying Dust First Nation - Connecting Communities - Flying Dust and Meadow Lake Walking Path Expansion

Flying Dust First Nation, Saskatchewan

completeActive TransportationCVRIS
Federal contribution
$1.7M
$1,724,938
Federal share75%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 6, 2021
202220232024
Built

Approved 7 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Flying Dust First Nation
Construction start
Aug 11, 2022(actual)
Construction end
Oct 31, 2024(actual)

Against the original forecast

  • Construction end2 months earlyforecast Dec 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59314 in the federal list. How to read these figures.