Rooftop Solar Power Upgrade - 3 Municipal Buildings and LED Lighting Upgrades
Federal contribution
$414,151
Federal share40%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
202220232024
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Moose Jaw
- Construction start
- Jan 11, 2022(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast Nov 22, 2021
- Construction end4 weeks earlyforecast Dec 31, 2023