Town of Wilkie - Community Centre and Ice Plant - Solar Power Upgrade
Federal contribution
$138,871
Federal share40%
of $347.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
2022
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Wilkie
- Construction start
- Aug 2, 2021(actual)
- Construction end
- Jun 15, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2021
- Construction end4 months earlyforecast Sep 30, 2022
Also in Wilkie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59328 in the federal list. How to read these figures.