Wastewater Systems Replacements - Westilse & Ellerslie Schools
Ellerslie-Bideford, Prince Edward Island
Federal contribution
$428,000
Federal share80%
of $535.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 17, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Government of Prince Edward Island
- Construction start
- Jul 5, 2021(actual)
- Construction end
- Sep 9, 2021(actual)
Against the original forecast
- Construction end6 weeks lateforecast Jul 27, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59335 in the federal list. How to read these figures.