Access PEI Summerside - Heating System Upgrade

Summerside, Prince Edward Island

completeVentilationCVRIS
Federal contribution
$180,000
Federal share80%

of $225.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 17, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 28, 2021(actual)
Construction end
Oct 18, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 15, 2021
  • Construction end4 months lateforecast Jun 24, 2022