Access PEI Summerside - Heating System Upgrade
Summerside, Prince Edward Island
Federal contribution
$180,000
Federal share80%
of $225.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 17, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Government of Prince Edward Island
- Construction start
- Sep 28, 2021(actual)
- Construction end
- Oct 18, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 15, 2021
- Construction end4 months lateforecast Jun 24, 2022
Also in Summerside