Resort Village of Turtle View - Municipal Office Retrofit and Fire Hall Addition

Resort Village of Turtle View, Saskatchewan

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$188,000
Federal share40%

of $470.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 6, 2021
2022
Built

Approved 7 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 12, 2021(actual)
Construction end
Oct 31, 2022(actual)

Against the original forecast

  • Construction start6 months earlyforecast Apr 1, 2022