Resort Village of Thode - Community Centre Upgrade
Federal contribution
$258,328
Federal share40%
of $645.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
202220232024
Built
Approved 7 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Resort Village of Thode
- Construction start
- Sep 15, 2021(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2021
- Construction end3 months lateforecast Aug 31, 2023