Resort Village of Shields - Municipal Sport Court Amenity/Maintenance Building Retrofit

Shields, Saskatchewan

completeRecreationCVRIS
Federal contribution
$61,303
Federal share40%

of $153.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 6, 2021
2022
Built

Approved 7 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Resort Village of Shields
Construction start
Oct 1, 2021(actual)
Construction end
Aug 31, 2022(actual)

Against the original forecast

  • Construction end4 months lateforecast May 1, 2022

Also in Shields

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59395 in the federal list. How to read these figures.