Retrofit of the Selwyn Municipal Office Entrance

Smith-Ennismore-Lakefield, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 17, 2021(actual)
Construction end
Dec 1, 2023(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 3, 2021
  • Construction end13 months earlyforecast Dec 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59399 in the federal list. How to read these figures.