Barrier Doors

Brethour, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$2,400
Federal share80%

of $3.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Brethour
Construction start
May 4, 2022(actual)
Construction end
May 5, 2022(actual)