Rural Municipaliltly of Golden West No. 95, King Bridge Replacement
Golden West No. 95, Saskatchewan
Federal contribution
$55,011
Federal share17%
of $330.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 13, 2021
20222023
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Golden West No. 95
- Construction start
- Oct 27, 2022(actual)
- Construction end
- Jun 7, 2023(actual)
Against the original forecast
- Construction start8 weeks lateforecast Sep 1, 2022
- Construction end2 months lateforecast Mar 31, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59422 in the federal list. How to read these figures.