Back to projects

RM of Spy Hill No. 152, Grid 600 Bridge Replacement

Spy Hill No. 152, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$166,700
Federal share17%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2022
20222023
Built

Approved 9 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Nov 1, 2022(actual)
Construction end
Apr 30, 2023(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Dec 5, 2022
  • Construction end2 months lateforecast Feb 28, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59428 in the federal list. How to read these figures.