RM of Spy Hill No. 152, Grid 600 Bridge Replacement
Spy Hill No. 152, Saskatchewan
Federal contribution
$166,700
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2022
20222023
Built
Approved 9 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Spy Hill No. 152
- Construction start
- Nov 1, 2022(actual)
- Construction end
- Apr 30, 2023(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Dec 5, 2022
- Construction end2 months lateforecast Feb 28, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59428 in the federal list. How to read these figures.