Rural Municipality of Baildon No. 131, Briercrest Woodbox Culvert Replacement
Federal contribution
$28,478
Federal share17%
of $170.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 13, 2021
20222023
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Baildon No. 131
- Construction start
- Jun 1, 2022(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast Oct 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59430 in the federal list. How to read these figures.