Back to projects

Rural Municipality of Baildon No. 131, Briercrest Woodbox Culvert Replacement

Baildon No. 131, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$28,478
Federal share17%

of $170.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 13, 2021
20222023
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jun 1, 2022(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction end2 months lateforecast Oct 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59430 in the federal list. How to read these figures.