Schedule

Announced and approvedApr 16, 2021
20222023
Built

Approved 3 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 27, 2021(actual)
Construction end
Oct 31, 2023(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Mar 31, 2021
  • Construction end3 months lateforecast Jul 31, 2023