Rural Municipality of Rosedale No. 283, Hanson's Culvert Replacement

Rosedale No. 283, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$29,376
Federal share17%

of $172.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2022
20222023
Built

Approved 9 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
May 1, 2023(actual)
Construction end
Aug 31, 2023(actual)