Rural Municipality of Buckland No. 491, Buckland Bridge Replacement

Buckland No. 491, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$166,670
Federal share17%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 13, 2021
2022
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Sep 15, 2021(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2022

Also in Buckland No. 491

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59611 in the federal list. How to read these figures.