Village of Lipton - Flooding Drainage Repair
Federal contribution
$60,400
Federal share40%
of $151.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Village of Lipton
- Construction start
- Apr 4, 2022(actual)
- Construction end
- Nov 9, 2022(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Nov 30, 2022
Also in Lipton