Outdoor Learning Spaces
Federal contribution
$5.5M
$5,473,824
Federal share80%
of $6.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 13, 2021
20222023
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- May 1, 2021(actual)
- Construction end
- Oct 30, 2023(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 31, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59666 in the federal list. How to read these figures.