Redevelopment of the site
Federal contribution
$480,000
Federal share80%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Jun 16, 2021(actual)
- Construction end
- Oct 29, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 15, 2021
- Construction end4 weeks earlyforecast Nov 27, 2021
Also in Pointe-Calumet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59690 in the federal list. How to read these figures.