Replacement of HVAC Units - Pyramid Centre

St. Marys, Ontario

completeVentilationCVRIS
Federal contribution
$101,358
Federal share80%

of $126.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of St. Mary's
Construction start
Oct 1, 2022(actual)
Construction end
Jan 12, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast May 9, 2022
  • Construction end7 months lateforecast May 31, 2022

Also in St. Marys