Swinging Bridge Repairs (Pedestrian Foot Bridge)
Federal contribution
$146,938
Federal share80%
of $183.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
Built
Approved 6 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Renfrew
- Construction start
- Oct 1, 2021(actual)
- Construction end
- Dec 1, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2021
- Construction end4 weeks earlyforecast Dec 31, 2021
Also in Renfrew
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59754 in the federal list. How to read these figures.