Back to projects

Modifications to the Municipal Building

Burpee and Mills, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
20222023
Built
Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2022(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction end2 months lateforecast Oct 30, 2022

Also in Burpee and Mills