Rehabilitation of Municipal Fire Stations
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of Grey Highlands
- Construction start
- Sep 17, 2021(actual)
- Construction end
- Feb 16, 2023(actual)
Against the original forecast
- Construction end7 weeks lateforecast Dec 31, 2022