Replace HVAC/Humidifiers - Trillium Manor
Federal contribution
$150,000
Federal share80%
of $187.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- The Corporation of the County of Simcoe
- Construction start
- Jul 16, 2021(actual)
- Construction end
- Oct 28, 2022(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 31, 2022
Also in Orillia
- Design and construct a new transit terminal$4.0M
- Construction of a Public Library and Market Square$1.9M
- Replace Conventional and Specialized Buses$1.8M
- Improvements to the Coldwater Water Distribution System$1.5M
- Upgrade the Wastewater Treatment Centre and Construct Tertiary Filter and Blower Buildings for Process Optimization, and Tertiary Treatment to meet Lake Simcoe Effluent phosphorus limits$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59780 in the federal list. How to read these figures.