2021-22 PEI TI Local Roads

Alberton, Prince Edward Island

completeHighways and RoadsRNIS
Federal contribution
$2.4M
$2,398,812
Federal share50%

of $4.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
Built

Approved 8 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jun 25, 2021(actual)
Construction end
Oct 8, 2021(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2021
  • Construction end4 weeks earlyforecast Nov 5, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59797 in the federal list. How to read these figures.