2021-22 PEI TI Local Roads
Alberton, Prince Edward Island
Federal contribution
$2.4M
$2,398,812
Federal share50%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
Built
Approved 8 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Construction start
- Jun 25, 2021(actual)
- Construction end
- Oct 8, 2021(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2021
- Construction end4 weeks earlyforecast Nov 5, 2021