Back to projects

Alberta Family and Senior Care Facilities Rehabilitation - Bundle 1 – Remote

Elk Point, Alberta

completeHealthcare InfrastructureCVRIS
Federal contribution
$850,160
Federal share80%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2021
20222023
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of Alberta
Construction start
Jun 2, 2021(actual)
Construction end
Sep 29, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2021
  • Construction end3 months earlyforecast Dec 31, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59801 in the federal list. How to read these figures.