Greenville Creek Sediment Mitigation

Nisga’a Village of Laxgalts’ap, British Columbia

completeDisaster MitigationCVRIS
Federal contribution
$247,238
Federal share100%

of $247.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 17, 2022(actual)
Construction end
Sep 30, 2024(actual)