Roof and Exterior Envelope Replacement
Federal contribution
$3.4M
$3,396,000
Federal share80%
of $4.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- May 17, 2021(actual)
- Construction end
- Aug 30, 2024(actual)
Against the original forecast
- Construction start5 weeks lateforecast Apr 15, 2021
- Construction end4 months earlyforecast Dec 31, 2024