Senior's Air Quality Systems (LTC and Rec Centre)
Federal contribution
$349,403
Federal share80%
of $436.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- County of Norfolk
- Construction start
- Nov 15, 2021(actual)
- Construction end
- Jul 31, 2023(actual)
Against the original forecast
- Construction end9 months lateforecast Oct 31, 2022
Also in Norfolk
- County Road 42 Road Rehibiliation$2.8M
- Replacement of Big Creek Bridge on Long Point Causeway$2.5M
- Re-Energizing Healthy Living: Retrofitting the Simcoe Seniors Recreation Centre for a Green and Inclusive Future$2.5M
- Port Rowan Water Treatment Plant Improvements$2.0M
- Building Sustainability: Port Rowan Community Centre Retrofits and Upgrades$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59918 in the federal list. How to read these figures.