Halton Community Housing Corporation Facility Upgrades

Burlington, Ontario

completeVentilationCVRIS
Federal contribution
$2.1M
$2,096,000
Federal share80%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2021
20222023
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 4, 2021(actual)
Construction end
Feb 10, 2023(actual)

Against the original forecast

  • Construction end3 months lateforecast Oct 28, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59943 in the federal list. How to read these figures.