Replacement of the boiler and the heating, ventilation and air conditioning system

Sainte-Marthe-sur-le-Lac, Quebec

completeVentilationCVRIS
Federal contribution
$2.6M
$2,640,000
Federal share80%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 22, 2021(actual)
Construction end
Sep 1, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 15, 2021
  • Construction end9 months lateforecast Dec 15, 2022

Also in Sainte-Marthe-sur-le-Lac

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59975 in the federal list. How to read these figures.