Municipal Complex Repairs and Upgrades
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Conmee
- Construction start
- May 3, 2021(actual)
- Construction end
- Dec 17, 2021(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Dec 31, 2021
Also in Conmee