Improve air quality for Tenants, Residents & Staff

Huron, Ontario

completeVentilationCVRIS
Federal contribution
$162,624
Federal share80%

of $203.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
County of Huron
Construction start
Apr 11, 2022(actual)
Construction end
Sep 30, 2023(actual)

Against the original forecast

  • Construction end16 months lateforecast May 19, 2022

Also in Huron

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60030 in the federal list. How to read these figures.