Retrofit Ginza Recreation Facility
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
20222023
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Greater Madawaska
- Construction start
- Sep 1, 2021(actual)
- Construction end
- Dec 31, 2022(actual)
Also in Greater Madawaska
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60037 in the federal list. How to read these figures.