Interior finish repair

Saint-Élie-de-Caxton, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$388,000
Federal share80%

of $485.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 3, 2021(actual)
Construction end
Jul 19, 2022(actual)

Against the original forecast

  • Construction end2 months earlyforecast Sep 30, 2022

Also in Saint-Élie-de-Caxton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60109 in the federal list. How to read these figures.